White and Eddy Building Surveyors Overlay effect

Building Regulations England Part L (BREL) Report

For residential building plans submitted to a Building Control body after 15th June 2022 there is now a requirement for a Building Regulations England Part L (BREL) report to be produced and for photographic evidence to be provided to the Building Control body and to the building owner to show that the building work complies with energy efficiency measures.

The BREL report will be carried out a by a competent Energy Assessor, however the photographs may be taken by either the developer, energy assessor or another individual.

Approved doc l

Who will take the photographs?

Photographs need to be taken for each dwelling on a development, with each photograph requiring to be date stamped and geo-tagged. Each image will also need to reference the numbers used in paragraph B7 (see below).

Design element

How does it work in practice?


The following is the list of the typical details of construction taken from Approved Document Part L, Conservation of fuel and power, Volume 1: Dwellings Appendix B7:

 

  1. Foundations/substructures and ground floor, to show thermal continuity and quality of insulation in the following places:
    1. At ground floor perimeter edge insulation
    2. At external door theshold
    3. Below damp-proof course on external walls
  2. External walls: for each main wall type, to show thermal continuity and quality of insulation for the following:
    1. Ground floor to wall junction
    2. Structural penetrating elements
  3. Roof: for each main roof type, to show thermal continuity and quality of insulation for the following:
    1. Joist/rafter level
    2. Eaves and gable ends
  4. Opening: for each opening type (one image per wall or roof type is sufficient), to show thermal continuity and quality of insulation with photographs of the following:
    1. Window positioning in relation to cavity closer or insulation line
    2. External doorset positioning in relation to cavity closer or insulation line
  5. Airtightness: additional photographs for all details 1-4 to show airtightness details (only if not included or visible in contunity of insulation image)
  6. Building services: for all plant associated with space heating, hot water, ventilation and low or zero carbon technology equipment within or on the building, show the following:
    1. Plant/identification label(s), including make/model and serial number
    2. Primary pipework continuity of insulation
    3. Mechanical ventilation ductwork continuity of insulation (for duct sections outside of the thermal envelope)
The White and Eddy team were always helpful and explained everything clearly. They came to site promptly and talked through any issues before directing me to the solutions. I feel confident having them check each stage of our build...